FHS Construction Timeline


Tentative Project Timeline

This project will happen over several years. Below you will find a tentative timeline for the completion of this project.

December 2016

  • FHS Staff completes tours of other district school buildings.

January 10, 2017

  • FHS Staff begins meeting with the architect team every other Tuesday through the end of March.

January 17, 2017

  • The Steering Committee meets at 8:00 AM in Room 110 at the high school. the meetings will last one hour. The public is welcome to attend. These meetings will be held every other Tuesday until the end of March.

April - November 2017

  • Architect team completes the design of the new facility and has drawings ready for the development of bid documents.

November 2017 - January 2018

  • The high school project is out for bid.

January - February 2018

  • Bids for the project are awarded.

March 2018

  • Vacate multipurpose room and three additional classrooms.
  • Start construction in that area.

April 2018

  • Start construction of the auditorium, boy's athletic team room, cafeteria, kitchen, two-story classroom area, weight room, and woodshop.

June 2018

  • Vacate the art, drafting, health, and woodshop classrooms.

August 2018

  • Occupancy begins for the art and drafting classrooms.

October 2018

  • Occupancy begins for the boy's athletic team room and weight room.

December 2019

  • Occupancy begins for the cafeteria, kitchen, two-story classroom area, and woodshop.

June 2019

  • Start science wing remodel.

August 2019

  • Occupancy begins for the science wing classrooms.

January 2020

  • Start demo of the west side of corridor B along with C, D, and F corridors.
  • Start demo of the locker room area.
  • Start construction on the girl's team room and robotics area.

February 2020

  • Start construction on the commons area, main/guidance offices, media center, and music area. 

August 2020

  • Occupancy begins for the girl's team room and robotics area.

April 2020

  • Occupancy begins for the auditorium.

February 2021

  • Start demo of the remaining locker room area.
  • Start construction of the MOCI kitchen area.
  • Start construction of the PE locker room area.

April 2021

  • Occupancy begins for the commons area, main/guidance offices, media center, and music area. 

May 2021

  • Start demo of the existing auditorium, main/guidance offices, media center, and the remaining section of corridor B.

August 2021

  • Occupancy begins for the MOCI kitchen and PE locker rooms.